 Day 1 Work Home Extension London Lavender Gardens

 

 

 Day 6 Work Home Extension London Lavender Gardens

 

24.04.2013 – Home Extension London Lavender Gardens

 

Home Extension London
Property Refurbishments London
Property Refurbishments London,
Home Extension London,

 

ESTIMATE

 

We supply all labour

Client supply materials deliveries etc.

All work warranted for 1 year.

All work insured for £5,000,000.

Terms: Payment will be divided after discussing with the client

Working hours: 8.00 am to 5.30 pm.

All work supervised by Pawel Raczkowski

New Extenison

DEMOLITION

Prepare existing home for demoliton.

Cover all floors with COREX floor covering.

Tent in area to be demolshed with plastic sheeting.

Remove all windows and glass.

Remove doors.

Bag all debris and move to kerbside for pickup.

Removal (skip) costs paid by customer.

FOUNDATIONS:

Carefully excavate existing concrete foundations.

Bag debris and move to kerbside for pickup.

Removal (skip) costs paid by customer.

Inspect existing ground.

As needed, dig out earth to 1m depth and 600 mm wide as per Regulations.

Arrange for inspection by Building Control.

After approval, pour new concrete foundations.

EXTENSION:

Install New Masonry(As Discussed / Per Plans – drawings)

INTERIOR/EXTERIOR CAVITY WALLS

Lay out face brick course as per plans on all exterior walls with light weight blocks
Lay out block courses as per plans on all interior walls with light weight blocks

WALL TIES

Install wall ties as directed. In order to comply with the requirements of the
Build­ing Regulations (1985) the ties will be installed and spaced as follows: 600 mm horizontal spacing and 450mm vertical spacing to provide a density of 3.7 ties/m2. (or per plans)

INSULATION

Install insulation as directed. Wall to be insulated with 50 mm Wall mate insulation or similar (per plans)Insulation to be installed horizontally starting at the sill plate. We will ensure that there are no cold bridges at junctions and openings.(No stapling is required because the batts fit tightly between brick skin and blocks.)

AIR VENTS / WEEP HOLES

Air vents (air bricks) to be installed per plans.
Weep holes to be installed per plans (if required)

DOORS

Make openings for doors per plans. Install lintels for door openings and windows per plans (Does not include steel beams). It will be useful when laying out door openings if you can fashion a wood template or similar. We will request that customer sign off door openings as they are completed.

EXTENSION FLOORING

Install TYPE1 MOD harcore in floor base (50mm).

Hard back using wacker plate.

Install sand base.

Install waterproof floor membrane and lap into walls as per plans.

Arrange for building control inspection.

Pour concrete screed and install floor installation and final concrete as per plans.

ROOFING:

Install wood beam at edge of new roof

Install new 6 x 6 (or other) joists set at 350mm to form new roof
(make opening for toilet waste stack)

Cover roof and install insulation per plans

Install roof covering

Install new lead flashing incorporated into brick walls (if requied)

Install gutter and downspout

Part of the garden’s level will need to be brought down in order to be slightly below the building’s

floor level.

Arrange for inspection by Building Control and provide all necessary building control certificates

where required

Plumbing :

– 1 no radiator

(This work will be undertaken in accordance with plans provided)

Painting and decorating new extension :

Painting walls and ceiling

Application of 3 coats of white emulsion (or other colour) on walls and ceilings

Painting Woodwork:

Repair wood trim on doors and doors if needed

Painting skirting

Scrape, fill and sand if needed

Application of 2 undercoats and 2 finishing coats (gloss or satin)

Doors

Install wood architrade on both sides of new doors.
Install hunges, door handles, and door locks on doors.

Steel Beams :

This work will be undertaken in accordance with plans provided

Arrange for inspection by Building Control and provide all necessary building control certificates

where required

Bedroom 1

Make openings and install lintels for doors.

Install doors.

Install one radiator to the new bedroom.

Move the existing radiator of the existing bedroom to its new location.

Install wood architrade on both sides of new doors.
Install hunges, door handles, and door locks on doors.

Painting walls and ceiling

Application of 3 coats of white emulsion (or other colour) on walls and ceilings

Painting Woodwork:

Repair wood trim on doors and doors if needed

Painting skirting

Scrape, fill and sand if needed

Application of 2 undercoats and 2 finishing coats (gloss or satin)

Bathroom

0, 9 cm x 260 cm

To erect a partition with soundproofing,

This job will be completed  according to client’s specification

Fit plasterboards
Preparing interior walls for new tiling

Installing new wall tiles
Preparing interior floor for new tiling

Installing new floor tiles

Installing new sink

Installing new shower.

Fiting shower screen if needed

Installing a new mirror if needed

This job will be completed  according to client’s specification.

Fixing ventilator

Instalation new frame and door

Make conection for ventilation pipe

Applying Silicone in all areas around shower, sink, toilet, etc…

Painting walls and ceiling if necessary

on the walls and ceilings applying 3 coats white emulsion (or other colour)

Completing Clean-up.

Utility room

Make utlity room according to plans.

Move existing boiler to its new position and install flue.

+  CORGI  certificate

Install washing machine.

Instalation new frame and door

Painting walls and ceiling if necessary

on the walls and ceilings applying 3 coats white emulsion (or other colour)

Install wood architrade on both sides of new doors.
Install hunges, door handles, and door locks on doors.

Completing Clean-up.

Hallway

Move the existing radiator of the hallway to its new location.

Painting walls and ceiling if necessary

on the walls and ceilings applying 3 coats white emulsion (or other colour)

Install wood architrade on both sides of new doors.
Install hunges, door handles, and door locks on doors.

Completing Clean-up.

Out side House :

Install a garden tap and power socket at the external wall of the new extension.

Electricity :

New extenison :

  1. 2 no double sockets
  2. 1 no down light

Bathroom

  1. 1 no down light
  2. 1 no extraction fan

Utility room

  1. 1 no double socket

 